§ 115A.37 — Final Decision of Board

Plain-Language Summary

This law gives the Environmental Quality Board the final word on whether a waste facility can be built. If the board approves a facility, its decision overrides local ordinances and zoning rules. The board can add stricter permit conditions than what state agencies required, and when agency requirements conflict, the stricter standard applies.

Practical Notes
Once the board approves a facility, no local government can block it. However, local governments can still impose reasonable conditions on construction and operation, subject to agency review. Permitting agencies must issue or amend permits within 60 days of the board’s decision to match the board’s terms.