In plain language
This section lets the Minnesota Public Utilities Commission make rules to carry out the state's power plant and transmission line siting law. It also requires the chief administrative law judge to set rules for public hearings on those site and route permits, with a goal of getting as much public input as possible within the legal deadlines.
Where this summary and the official text differ, the official text controls.
What this means for you
These rules shape how
site permits and
route permits for large energy projects, such as power plants and high-voltage power lines, are reviewed and decided. They matter most to
landowners,
local communities, and
residents who want to take part in hearings or propose
alternative routes or sites. The section also says rules cannot favor
state-owned wildlife management areas over
agricultural lands when designating route avoidance areas.
Text of the law
Subdivision 1. Commission rules.
The commission, in order to give effect to the purposes of this chapter, may adopt rules consistent with this chapter, including promulgation of site and route designation criteria, the description of the information to be furnished by the utilities, establishment of minimum guidelines for public participation in the development, revision, and enforcement of any rule, plan, or program established by the commission, procedures for the revocation or suspension of a site or route permit, and the procedure and timeliness for proposing alternative routes and sites. A rule adopted by the commission must not grant priority to state-owned wildlife management areas over agricultural lands in the designation of route avoidance areas. Chapter 14 applies to the appeal of rules adopted by the commission to the same extent as it applies to review of rules adopted by any other agency of state government.
Subd. 2. Court of Administrative Hearings rules.
The chief administrative law judge must adopt procedural rules for public hearings relating to the site and route permit process. The rules must attempt to maximize citizen participation in these processes consistent with the time limits for commission decision established under this chapter.
History: 1973 c 591 s 16; 1975 c 271 s 6; 1977 c 439 s 22; 1978 c 658 s 2; 1982 c 424 s 130; 1984 c 640 s 32; 2001 c 212 art 7 s 27; 2005 c 97 art 3 s 19; 2024 c 126 art 7 s 14; art 9 s 15; 2024 c 127 art 43 s 14; art 45 s 15; 2025 c 39 art 2 s 68