In plain language
The developer must complete all improvements labeled 'MUST BE BUILT' and must repair any damage caused during construction.
Where this summary and the official text differ, the official text controls.
What this means for you
If the community plat says something must be built, the developer is legally required to finish it and fix any construction damage.Text of the law
No promotional material may be displayed or delivered to prospective purchasers which describes or portrays an improvement that is not in existence unless the description or portrayal of the improvement in the promotional material is conspicuously labeled or identified either as “MUST BE BUILT” or as “NEED NOT BE BUILT.”
History: 1993 c 222 art 4 s 17
1993 c 222 art 4 s 17