§ 103D.801 — Procedure When Contract is Not Let

Plain-Language Summary

If all bids for a project are more than 30% above the engineer's estimate or exceed the net benefits, the managers must follow the procedure in section 103E.511, which typically involves rebidding or modifying the project.

Practical Notes
This prevents projects from proceeding when costs have exceeded expectations. The 30% threshold and the benefits-minus-damages limit are separate triggers. If either is exceeded, the managers must follow section 103E.511’s procedures rather than simply awarding the contract.