This chapter is called the Minnesota Energy Infrastructure Permitting Act, a law that took effect July 1, 2025. It replaced the previous energy siting laws found in chapters 216E and 216F. The Act sets up a single permitting system for large power plants, wind and solar farms, energy storage facilities, and high-voltage power lines in Minnesota.
216I.01 CITATION.
This chapter may be cited as the “Minnesota Energy Infrastructure Permitting Act.”
History:
2024 c 126 art 7 s 1; 2024 c 127 art 43 s 1
History: History: 2024 c 126 art 7 s 1; 2024 c 127 art 43 s 1
Practical Notes
Anyone working on a large energy project in Minnesota that was started before July 1, 2025, should check whether their project is governed by the old chapters 216E and 216F or by this new Act. The name ‘Minnesota Energy Infrastructure Permitting Act’ is important for citing the law in permit applications, environmental documents, and legal filings.