§ 216I.07 — Applications; Standard Review

Plain-Language Summary

This section establishes a faster 'standard review' process for certain types of energy projects, including smaller power plants (under 80 MW), natural gas plants, transmission lines between 100 and 300 kV, most solar and wind farms, and energy storage systems. Under standard review, the applicant prepares the environmental assessment rather than the PUC, and the PUC must make a final decision within six months of accepting the application as complete. A public hearing is still required.

Practical Notes
Most solar, wind, and battery storage projects will qualify for the shorter standard review process under this section, which has a six-month decision deadline compared to one year for major review. Developers should elect standard review at the time of filing to lock in the faster timeline. The applicant bears more of the environmental review burden under this process, so preparing a thorough environmental assessment is important.